News Item

TransGrid Publishes NSTNA Report - Sydney West 132 kV Fault Interruption Capability

22 December 2006

TransGrid is proposing the construction of a New Small Transmission Network Asset and has published a report pursuant to clause 5.6.6A(c) of the National Electricity Rules. The proposal is to replace selected 132 kV equipment at Sydney West 330/132 kV Substation to achieve a fault minimum fault interruption capability of 38 kA for all 132 kV equipment. TransGrid invites submissions from interested parties on this proposal. The last date for submissions is 24th January 2007.

The report can be downloaded from the Link to Current ConsultationsCurrent Consultations page.