TransGrid is constructing a new transmission line between Manildra and Parkes. The $30 million project is necessary to ensure high levels of reliability to ensure that customers in the Central Slopes and Plains region continue to enjoy a reliable electricity supply.

 

TransGrid has appointed contractor Downer EDI to construct 81 kilometres of transmission line from the Manildra substation to Parkes substation. 

 

During the corridor selection process, a preferred corridor of 1-2 kilometres in width was identified that provided the best social, environmental, technical and economic option available for the routing of the proposed power line and poles.

 

Additional environmental studies were also carried out and consultation with landholders were undertaken, before an alignment within a 45 metre wide easement was identified for further engineering and environmental studies. In developing this alignment, all affected landholders were individually consulted during the detailed design and environmental studies of the route.

 

Along with our environmental consultants URS, we would like to thank all landholders, community members and interest groups who have attended the public information sessions, met with us and provided valuable feedback to the team since the project was first announced. The results of the studies were detailed in two Environmental Assessment documents: a Review of Environmental Factors (REF) and a Species Impact Statement (SIS). Both of these documents, in addition to a Summary Document, are provided below.   

 

These documents were on public exhibition between 29 July and 27 August 2009. The aim of the exhibition was to give the community an opportunity to review the document and provide final comments on the proposal. Key issues raised in these submissions have been considered by TransGrid and the project has been approved under Part 5 of the Environmental Planning and Assessment Act (NSW).

 

Project Updates

 Name Date View
Community Update Nov 2011 PDF
Community Update July 2011 PDF
Community Update Jan 2011 PDF
Community Update Sept 2010 PDF
Fact Sheet July 2009  PDF
Application Notice July 2007  PDF
Final Report Nov 2007  PDF

 

Review of Environmental Factors (REF) 

 Name Date View
Table of Contents  July 2009   PDF
Executive Summary July 2009  PDF
Introduction July 2009  PDF
Planning Context July 2009  PDF
Environmental Impact Assessment July 2009  PDF
Topography (Figures 7.1 - 7.4) July 2009  PDF
Survey Locations (Figures 7.5 - 7.6) July 2009  PDF
Endangered Ecological Communities (Figures 7.7a - 7.7d) July 2009  PDF
Endangered Ecological Communities (Figures 7.7e - 7.7f) July 2009  PDF
Endangered Ecological Communities (Figures 7.7g - 7.7j) July 2009  PDF
Recorded Sites July 2009  PDF
Landscape Units Sheet July 2009  PDF
Illustrative Photomontage Locations July 2009  PDF
Conclusion July 2009  PDF
References July 2009  PDF
Abbreviations and Glossary July 2009  PDF
Appendix A - Route Selection Map July 2009  PDF
Appendix B - Consultation Report Part 1 July 2009  PDF
Appendix B - Consultation Report Part 2 July 2009  PDF
Appendix B - Consultation Report Part 3 July 2009  PDF
Appendix C - Referral Decision July 2009  PDF
Appendix D - Indigenous and Non-Indigenous Heritage Assessment July 2009  PDF
Appendix E - Landscape and Visual Impact Assessment July 2009  PDF
Appendix F - Easement and Access Track Maintenance Policy July 2009  PDF
Appendix G - Planning, Consultation and Maintenance July 2009  PDF
Appendix H - Department of Urban Affairs and Planning Assessment July 2009  PDF

 

Species Impact Assessment (SIS) 

 Name Date View
 Main Report July 2009  PDF
 Appendices July 2009  PDF
Species Impact Statement Part 2 July 2009  PDF
Species Impact Statement Part 3 July 2009  PDF

 

REF and SIS Summary Document

 Name Date View
Summary Document July 2009  PDF

Project contact

1800 851 299

Subscribe to updates

* indicates a required field

First Name *

Last Name *

Email Address *

 
Please enter the text 'exactly' as shown below.

Captcha Image

Refresh Image | What's this?

Terms & Conditions | Privacy Statement

© Copyright 2009 TransGrid. All rights reserved.