The Western Sydney Supply Project (WSSP) is one part of a five year plan to secure Sydney’s power supply for the future. The project is necessary to ensure a continued reliable supply of electricity to the city and the greater Sydney area.
The WSSP includes:
- Construction of the new Holroyd Substation at Greystanes;
- An upgrade to the existing overhead transmission line between Sydney West Substation at Eastern Creek and the new Holroyd Substation;
- Construction of the new Rookwood Road Substation at Potts Hill; and
- Construction of a new underground electricity cable between the two new substations.
Where are we up to?
The Western Sydney Supply Project is the most practical and cost effective solution to overcome the limitations in the transmission network in the Sydney area, and the project will proceed. Final planning, design and environmental approvals are completed. Construction has commenced on the new substations and TransGrid will start work on the transmission line upgrade and new electricity cables mid 2012.
Update on the Holroyd Substation
The new Holroyd Substation will be built on Hyland Road, Greystanes in the south western corner of Hyland Road Regional Park - the former home of a pigeon club and rifle range facility. Construction on the new substation is expected to start in September 2011. Two transformer deliveries are scheduled for mid 2012.
Update on the transmission line upgrade
The existing transmission line from Sydney West Substation at Eastern Creek will be upgraded to operate at a higher voltage. The upgrade will allow TransGrid to meet the growing electricity needs of Sydney as the population increases. New sections of the transmission line will be built to connect into the new Holroyd Substation and to connect into Sydney West Substation at Eastern Creek. Work is expected to begin on the transmission line upgrade in the second quarter of 2012.
Update on the Rookwood Road Substation
The new substation is being built on Rookwood Road, Potts Hill in the new Potts Hill Business Park. Construction on the new substation is expected to commence in September 2011. Three transformer deliveries are expected between late December 2012 and early 2013.
Update on the underground cable
The 15 kilometre electricity cables will be buried underground between Holroyd Substation and Rookwood Road Substation. TransGrid proposes to install the cables along the Sydney Water pipeline corridor from Guildford to Potts Hill and alongside the Canal Reserve Cycleway between Holroyd and Guildford. As a result, the cables will not pass under any residential properties. If the project is approved, we will begin work on the underground cables in mid 2012.
Keeping you informed
At TransGrid, we are committed to keeping residents and businesses informed about the project. Regular community updates will be delivered to residents and businesses to keep them up to date as the project progresses.
Project updates
| WSSP Community Update |
May 2012 |
PDF |
| WSSP Community Update |
December 2011 |
PDF |
| WSSP Community Update |
July 2011 |
PDF |
| WSSP Community Update |
April 2011 |
PDF |
| Map - Western Sydney Supply Project Corridor |
February 2011 |
PDF |
| Rookwood Road Substation - Review of Environmental Factors (Advertisement) |
June 2010 |
PDF |
| Holroyd Substation - Review of Environmental Factors (Advertisement) |
June 2010 |
PDF |
| WSSP Community Update |
May 2010 |
PDF |
| Final Report - Development of Electricity Supply to the Sydney CBD and Inner Metropolitan Area |
March 2010 |
PDF |
| Project Announcement Letter to Residents and Businesses - Transmission Line Upgrade |
March 2010 |
PDF |
| Project Announcement Letter to Residents and Businesses - Underground Cable |
March 2010 |
PDF |
| Fact Sheet - Rookwood Road Substation |
December 2009 |
PDF |
| Fact Sheet - Holroyd Substation |
December 2009 |
PDF |
| Fact Sheet - Holroyd to Rookwood Road Underground Cable |
December 2009 |
PDF |
| Fact Sheet - Sydney West to Holroyd Transmission Line Upgrade |
December 2009 |
PDF |
| Fact Sheet - Request for Proposals |
December 2009 |
PDF |
| Community Update |
December 2009 |
PDF |
| Request for proposals (RFP) 105/09 - Development of Electricity Supply to the Sydney CBD and Inner Metropolitan Area |
December 2009 |
LINK |
| Application Notice - Development of Electricity Supply to the Sydney CBD and Inner Metropolitan Area |
December 2009 |
PDF |
| Demand Management Investigation Report - Sydney Inner Metropolitan Area |
November 2009 |
PDF |