Mount Piper to Wallerawang

Construction starts on critical link to unlock cleaner, lower-cost power

18 November 2026

Construction of an essential new transmission line is underway in the Central Tablelands to help deliver more affordable and reliable power from NSW’s first renewable energy zone to homes and businesses across the state.

Transgrid and its construction partner Zinfra are delivering the 8km Mt Piper to Wallerawang Transmission Line Upgrade Project as part of network augmentations to support EnergyCo’s Central West-Orana Renewable Energy Zone.

Executive General Manager of Delivery Jennifer Hughes said the project would upgrade the existing 132 kV transmission line with modern 330 kV infrastructure to significantly increase power transfer capacity and help unlock new renewable energy for consumers.

"We are getting on with the job of delivering critical new transmission infrastructure to help realise the NSW Government’s energy vision and transition the state to an affordable, reliable and secure energy future," Ms Hughes said.

"Construction is expected to support up to 150 jobs and create opportunities for local workers, contractors and suppliers.

"Transgrid would like to thank the local community, landowners and stakeholders who participated in the planning and environmental assessment process.

"Their vital local knowledge helped inform the development of the project and selection of a route that makes extensive use of existing transmission easements and infrastructure corridors to help minimise impacts on surrounding land and vegetation.

"We will continue to work with EnergyCo and the local community to manage impacts carefully and unlock benefits for the local area throughout the delivery phase.

"The project also incorporates a range of measures to protect biodiversity, waterways and cultural heritage values during construction."

Transgrid's construction partner Zinfra started construction this week. The initial works include site establishment, vegetation clearing and access track construction.

"Zinfra is fully committed to delivering the Mount Piper to Wallerawang Transmission Line Upgrade Project in line with the Environmental Impact Statement, working closely with local communities to minimise impacts on landowners, residents and the environment wherever possible," Zinfra General Manager Tim Byrne said.

"Importantly, we also want the project to deliver meaningful benefits for the region by creating local employment opportunities and engaging local subcontractors and suppliers."

For more information: https://www.transgrid.com.au/projects-innovation/central-west-orana-renewable-energy-zone-network-upgrades/

Project fast facts

  • An 8km double-circuit overhead transmission line supporting 330 kV and 132 kV transfer
  • 32 new transmission structures and approximately 90km of conductor cabling
  • Two temporary construction compounds
  • Up to 150 construction jobs
  • Supply contracts for local businesses
  • Strict conditions of approval to minimise community and environmental impacts
  • Construction expected to be completed by July 2028
  • Supports delivery of 4.5 GW of generation from the NSW Government’s Central West-Orana Renewable Energy Zone.

Media enquiries: Mark Nolan – 0429 047 136