Overview

Communities across the Far West will benefit from action to strengthen the region’s back up power supply through the delivery of important energy solutions. The Far West Project will help ensure Broken Hill and Far West NSW communities are not reliant on any single high-voltage back-up power source in the event electricity supply from the X2 220kV transmission line from Buronga to Broken Hill is disrupted. The NSW Minister for Energy and Environment issued a Ministerial Direction on 29 January 2026, classifying the Far West Project as a Priority Network Infrastructure Project under the NSW Electricity Infrastructure Investment Act 2020.

Project benefits

This project will initially deliver additional sources of high-voltage electricity generation, providing further back-up capacity, which meets the minimum power requirements of the Broken Hill 220kV substation in the event supply from the X2 transmission line is unavailable.

Ultimately, it will provide connectivity to alternate sources of back-up power supply to give communities in Far West NSW confidence of a reliable power supply.

This is in accordance with a key finding of the Parliamentary Inquiry into the October 2024 extreme weather event and outage. Transgrid is working closely with the Department of Climate Change, Energy, the Environment and Water (DCCEEW) to deliver this Priority Network Infrastructure Project for the Far West region, across two stages:

Interim Solution: Installation of additional temporary generation infrastructure to provide a secondary back-up to the existing gas turbine generators to further support the minimum power requirements of the Broken Hill substation when the X2 transmission line is not available.

Long-term Solution: Replacement of the existing gas turbine generators with alternate solutions which meet minimum power requirements of the Broken Hill substation when Transmission Line X2 is not available. We are working with DCCEEW on this solution and will share more information as this work progresses.

Where are we now?

Transgrid is progressing the Interim Solution with the proposed installation of a series of temporary diesel reciprocating engines (generators) at the Broken Hill 220kV substation during 2027. This solution will provide a combined generating capacity of 40 megawatts (MW) and provide a secondary back-up to the gas turbine generators at the substation.

Transgrid has started procuring long-lead equipment to keep the project on track. Delivery of the Interim Solution remains subject to the outcome of the REF process.

Timeline

  • Project development - In progress

    Early-late 2026

  • Initial consultation on proposed Interim Solution - In progress

    Late 2026

  • Review of Environmental Factors published and public submissions invited - Proposed

    January 2027

  • REF community information sessions in Broken Hill as part of REF submissions - Proposed

    February 2027

  • REF Submission Report published - Proposed

    March 2027

  • Project determination and publication - Proposed

    April 2027

  • Interim Solution construction and commissioning - Proposed

    Late 2027

    * Indicative project timeline

Review of Environmental Factors

As part of the project development process Transgrid will be publishing a Review of Environmental Factors (REF). This report will examine the potential environmental, social, economic, and heritage impacts of the proposal and identify measures to mitigate these. The REF process applies to certain infrastructure projects and activities carried out by public authorities that are classified as development permitted without consent.

Community engagement

Transgrid is committed to keeping Far West NSW communities informed as we continue to work to strengthen the region’s energy future.

Community information sessions

Community information sessions are planned for Broken Hill in February 2027 as part of the REF exhibition period. This page will be updated with details of community engagement activities as they are confirmed.

Why energy supply in Far West NSW is uniquely challenging

We know people in Broken Hill and across the Far West of NSW have understandable concerns about power reliability, particularly after the extreme weather event in October 2024 that damaged transmission infrastructure.

Supplying electricity to the Far West is different to almost anywhere else in NSW. The region is connected to the National Electricity Market by a single high-voltage transmission line that runs about 260 kilometres from Buronga to Broken Hill. In most parts of the state, electricity can flow through several different transmission routes if one line is out of service. In Far West NSW, there is no alternative pathway.

This means that when the transmission line is offline, whether for planned maintenance or due to unexpected issues, there is no other way to bring power into Broken Hill from the grid. To manage this, two large back-up gas turbine generators are used to supply electricity locally while the line is out of service. This arrangement is unique within Transgrid’s network and reflects the engineering challenge of supplying power to a remote region over long distance.

Strengthening energy supply in the Far West is complex, but it is a high priority. We are fast-tracking new back-up generation for the region, and working with DCCEEW on longer-term storage solutions. These investments are about strengthening back-up supply to Far West NSW when the X2 transmission line is out of service.

Status of the gas turbine generators

The table below outlines the status of both gas turbine generators (GT1 and GT2).

GT1 Available for service
GT2 Available for service

(Last updated 26 October 2026 8:54 AM AEST)

Planned maintenance schedule for Broken Hill

Planned maintenance Date
Upgrade works at Buronga substation 6pm (ACST) 6:30pm (AEST) Friday 23 October – 6am (ACST) 6:30am (AEST) Monday 26 October

 

Summary of support after the 2024 extreme weather event

In October 2024, Transgrid announced $2 million in support to the communities affected by the extreme weather event that impacted power supply to the Far West region of NSW.

Transgrid launched a specialised Community Partnerships Program with $500,000 in new grants for community organisations and not-for-profit groups in Far West NSW. This was in addition to a multi million-dollar community support packaged in partnership with the NSW Government.

Contact us

Reporting a localised power outage

Contact Essential Energy 13 20 80 to report a disruption to residential or business supply.
Broken Hill

26 August 2025

Funding boost for Far West NSW communities

Community groups across Far West NSW are sharing in $200,000 in grants under the second round of Transgrid’s Far West NSW Community Partnerships Program, helping deliver projects that will create lasting value for the region.

Broken Hill

05 June 2025

Works on Broken Hill transmission line this weekend

Transgrid crews will be completing line works on the transmission line supplying Far West NSW this weekend.

Broken Hill

07 February 2025

Funding boost for community initiatives across Far West NSW

Community groups across Broken Hill and Far West NSW have received a much-needed funding boost to support local initiatives and deliver lasting social benefits with improved services, facilities, events and activities.